Skip to main content

Municipal Building Approval Process in Nepal: A Step-by-Step Guide

Getting your nakshe pass (building permit) approved in Nepal involves multiple steps across different government bodies. Here is the complete process explained for 2082 BS.

Construction Tips 11 views 2 min read

Municipal Building Approval Process in Nepal: A Step-by-Step Guide

Getting your nakshe pass (building permit) approved in Nepal involves multiple steps across different government bodies. Here is the complete process explained for 2082 BS.

Municipal Building Approval Process in Nepal: A Step-by-Step Guide

Overview of the Building Permit Process in Nepal

Before breaking ground on any structure in Nepal, you must obtain a building permit from your local government authority — Municipality (नगरपालिका) or Rural Municipality (गाउँपालिका). This permit, commonly called "nakshe pass," legally authorises your construction and ensures compliance with the National Building Code of Nepal (NBC 2060).

Documents Required

  • Lalpurja (land ownership certificate)
  • Nagarikta (citizenship certificate of all owners)
  • Plot map / field book (Thari napi naksha)
  • Architectural drawings (floor plan, elevation, section) — signed by a licensed architect
  • Structural drawings — signed by a licensed structural engineer
  • Site plan showing setbacks from all boundaries
  • Neighbour consent letter (if building near the boundary)

Step-by-Step Process

  1. Engage a licensed architect: Only a Nepal Engineering Council (NEC) registered architect can submit drawings for approval.
  2. Prepare drawings per NBC: Drawings must comply with the National Building Code, local floor area ratio (FAR), and setback requirements.
  3. Submit to Municipality: Submit the complete document package to the Ward Office or Municipality building department.
  4. Technical verification: The Municipality's technical officer verifies the drawings and site within 30 days (by law).
  5. Pay permit fee: Fees are calculated based on covered area and number of floors. Typically NPR 50,000–3,00,000 for a residential project.
  6. Receive nakshe pass: The approved permit is valid for construction as per the approved drawings. Any deviation requires amendment approval.
  7. Construction supervision: The architect must certify the construction at plinth level, DPC level, and on completion.

Common Reasons for Rejection

  • Insufficient setbacks from plot boundaries (varies by road width and municipality)
  • FAR exceeded (Floor Area Ratio limits vary by zone)
  • Structural drawings not matching architectural drawings
  • Documents not notarised or outdated

Vastuveda Designs handles the complete approval process for our clients — from drawing preparation to submission and follow-up. Contact us to learn more.

Tags: ["building-permit" "nakshe-pass" "nepal" "municipality" "construction"]
Sujita Dhungana

Written by

Sujita Dhungana

Lead Architect

View full profile →